Capital Projects
Projects
Every capital project — new campuses, expansions, renovations, and modular additions — with budget, schedule, and compliance status.
| Project | Campus | Funding | Budget | Phase | Status | Target open | Discuss |
|---|---|---|---|---|---|---|---|
| LRA Oakmont — New K-8 Campus CP-2026-001 · New Campus | LRA Oakmont (new) | Revenue Bond + Charter School Capital Outlay | $11,240,000 / $18,500,000 | Construction | On track | Aug 11, 2026 22d | |
| LRA Palmetto — 6-Classroom Modular Addition CP-2026-002 · Modular / Portables | LRA Palmetto Elementary | Charter School Capital Outlay | $420,000 / $1,420,000 | Permitting | At risk | Aug 11, 2026 22d | |
| LRA Oleta — Gym & Cafeteria Renovation CP-2026-003 · Renovation | LRA Oleta | Capital Fund + Facilities Safety Grant | $640,000 / $3,200,000 | Design | On track | Dec 15, 2026 148d | |
| LRA Coral Way — Pre-K Wing Buildout CP-2026-004 · Expansion from WO-2026-003 | LRA Coral Way | Early-Learning Grant + Lease | $1,680,000 / $2,100,000 | Construction | Delayed | Sep 1, 2026 43d |